Cement Transition Period in The Oil Well Can Cause Well Control Situation

When cement is in transition period (forming the bond), you will lose some hydrostatic pressure because cement becomes solid phase therefore water in the cement will provide hydrostatic pressure. In many cases happened, there is no issue while performing the cement job however once the cement is set after period of time, there is a casing pressure indicating that there is hydrocarbon in the annulus.

This example will demonstrate you why the well is in underbalance condition while waiting on cement.

Well information: Previous 9-5/8” casing shoe at 4000’ ft.

The vertical well (8.5” hole) is drilled to TD at 10,000ft with 12.1 ppg mud and the pay zone is at 9,800’ TVD with reservoir pressure of 11.6 ppg. The cement is planned to cover 3,500 ft in the annulus above the casing shoe. Water used to mix cement is 8.3 ppg weight.

 cement Transition Period

 

Will the well go underbalance during the cement in transition period?

 Formation pressure at 9,800 ft

Formation pressure at 9,800 ft = 0.052 x 11.6 x 9800 = 5,911 psi

Total hydrostatic pressure in the annulus

Hydrostatic pressure of drilling mud at 6,500 ft = 0.052 x 12.1 x 6,500 = 4,090 psi

When cement in transition period, only water in cement will provide hydrostatic pressure. So we can calculate hydrostatic pressure of water in cement

Hydrostatic pressure of water in cement = 0.052 x (9800 – 6,500) x 8.3 = 1,424 psi

While cement is in the transition period, total hydrostatic pressure in the annulus is equal to hydrostatic pressure of mud plus hydrostatic of water in cement

Total hydrostatic pressure in the annulus = 4,090 + 1,424 = 5,514 psi

 cement Transition Period 2

You will see that during the transition period total hydrostatic pressure in the annulus is less than formation pressure therefore the well. For this case, the well will flow during transition period.

 cement Transition Period 3

 

 

Ref books: Cementing Technology Books

Drilling Formula BookFormulas and Calculations for Drilling, Production and Workover, Second Edition

Related Post

Manifa Oilfield – Heavy Crude Field, Saudi A... Saudi Arabia has the second largest oil reserves in the world, so it is quite logical that there are several successful oil companies in this country....
What is “Background Gas”? While we are drilling, there is a stable gas reading that is not connected with either bottoms up gas or drilled gas is generally called “Background G...
Possible Kick (wellbore influx) Indications Part2 This is the second part of the possible kick indications that I would like to share with you. Decrease in d-Exponent Value Normally, trends of d...
Determine surge and swab pressure for open-ended p... You’ve learn how to determine surge and swab pressure from the previous topic (Surge and swab pressure method 1) and this topic will demonstrate you h...
Share the joy
  •  
  •  
  •  
  •  
  •  
  •  
  •  
  •  
  •  

About DrillingFormulas.Com

Working in the oil field and loving to share knowledge.
Tagged , , . Bookmark the permalink.

2 Responses to Cement Transition Period in The Oil Well Can Cause Well Control Situation

  1. Mufti says:

    Nice sharing you got here, really help me to understand flow after cement job while check valves on shoe is fails, can I use it on my writes ?
    I’ll entitled your website for my writes

    Regards

    Mufti Ghazali

  2. Monir says:

    Excellent example of under balance situation while WOC

Leave a Reply

Your email address will not be published. Required fields are marked *