Dilution of Mud System to Control Low Gravity Solid by Adding Mud

Adding bbl of  drillingfluid can help control low gravity solid (LGS) in mud system. However, this is different from the way to control LGS by adding base fluid as base oil or water because mud that is added into system has some Low Gravity Solid (LGS). Hence, when we calculate it, we need to account for Low Gravity Solid (LGS) of new mud into the calculation as well. This post will demonstrate you how to determine barrels of drilling fluid required to achive the desired Low Gravity Solid (LGS).

Formula, used to calculate dilution of mud system, is listed below;

Vwm = Vm x (Fct – Fcop) ÷ (Fcop – Fca)

Where; Vwm = barrels of dilution water or base fluid

Vm = total barrels of mud in circulating system

Fct = percent low gravity solids in system

Fcop = percent total low gravity solids desired

Fca = percent low gravity solids bentonite and/or chemicals added in mud

Example: Determine how much barrels of oil base mud to diluate total 2000 bbl of mud in system from total LGS = 7 % to desired LGS of 3.5 %. The oil base mud has 2% of bentonite slurry.

Vwm = Vm x (Fct – Fcop) ÷ (Fcop – Fca)

Vwm = 2000 x (7 – 3.5) ÷ (3.5-2)

Vwm = 4667 bbl

In order to dilute total of 2000 bbl of the original mud with 7% LGS down to 3.5% LGS, 4667 bbl of mud that has 2% bentonite is requied to add into the system.

Please find the excel sheet used to calculate how much barrel of drilling fluid to control Low Gravity Solid (LGS) in mud system.

Ref book: Drilling Formula Book Formulas and Calculations for Drilling, Production and Workover, Second Edition

Directional Drilling Books

Related Post

Lag Time for Drilling Business and How to Calculat... I got an email from Sanan asking me about how to calculate lag time. First of all, you need to know what the lag time is. Lag time is traveling t...
Maximum Initial Shut-In Casing Pressure (MISICP) Maximum Initial Shut-In Casing Pressure (MISICP) or Maximum allowable shut in casing pressure is the initial shut-in casing pressure that will exceed ...
Calculate Influx Height Once you know how much pit gain you got, you are able to determine influx height. Please take a look at the figure below for more understanding. &n...
Surface Pressure During Drill Stem Test Drill stem test or well test is mostly conducted for exploration wells in order to see how much hydrocarbon can be produced for the reservoir, estimat...
Share the joy
  • 13
  •  
  •  
  •  
  •  
  •  
  •  
  •  
  •  
    13
    Shares
Tagged . Bookmark the permalink.

About DrillingFormulas.Com

Working in the oil field and loving to share knowledge.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.