Kill Weight Mud

Kill Weight Mud or Kill Drilling Fluid Density is the mud weight required to balance formation pressure. The kill weight mud may be pumped into the well at different time depending on kill methods (Driller’s method, Wait and Weight, Bull head, etc).

 kill weight mud cover

How to determine kill weight mud?

With the following equation, you can determine this figure.

 

Kill Weight Mud (KWM) = Current Mud Weight + (SIDPP ÷ 0.052 ÷ Well TVD)

Where,

Kill Weight Mud (KWM) in ppg

Current Mud Weight in ppg

SIDP stands for “Shut In Drill Pipe Pressure” in psi.

Well TVD is true vertical depth of the well in ft.

Example:  Drilling with 9.5 ppg mud and current depth at 9,500’MD/9,000’ TVD. The well takes influx. Operation is stopped and the well is shut in.

Shut in drill pipe pressure = 500 psi.

Shut in casing pressure = 700 psi.

What is the kill weight mud?

 kill weight mud

The kill weight mud required to balance formation pressure:

Kill Weight Mud (KWM)  = 9.5 + (500 ÷ 0.052 ÷ 9,000)

Kill Weight Mud (KWM) = 10.6 ppg (round up number)

 

Why do we need to use SIDPP?

When you take a kick (wellbore influx), the density of fluid in the annulus is very hard to predict because it is a mixture between drilling mud and influx. Therefore, you don’t know exactly what the density in the annulus is. Moreover if you take gas kick, shut in casing pressure will increase over time, and you will NOT be able to identify the right shut in pressure to determine formation pressure.

Looking at the drill pipe side, there is only one pure fluid column so you know exactly its density. With the precise mud density, you can apply hydrostatic pressure concept in order to get the formation pressure and kill weight mud (the equation is showed at the beginning of the topic).

Note: If your drilling string has a solid float, you will not be able to read SIDPP right away. So you need to bump the float to get SIDPP. You can read more detail about it via this > float bumping procedure.

 

Reference book: Drilling Formula BookFormulas and Calculations for Drilling, Production and Workover, Second Edition

Related Post

Pressure Profile of Drillpipe and Casing Pressure ... This topic will cover about pressure profile both drill pipe and casing pressure while kill a well with wait and weight method.   Drill Pip...
Calculate Cement (Oil Well Cement) Volume Required Cement volume calculation is based on annular capacity multiplied by length of cement as per cement program. This topic will demonstrate you how to de...
Why Do We Need To Minimize Influx (Kick)? As you know, we’ve always been trained or told to minimize influx (kick). Nowadays, there are several tools and procedures guiding us to prevent large...
Practice to drill the well at near balance conditi... In some situation, where you drill with mud weight that is very close to balance condition (near formation pressure) and you don’t have much room to w...
Share the joy
  • 560
  •  
  •  
  • 15
  •  
  •  
  •  
  •  
  •  
    575
    Shares

About DrillingFormulas.Com

Working in the oil field and loving to share knowledge.
Tagged , , , . Bookmark the permalink.

4 Responses to Kill Weight Mud

  1. Pingback: Maximum pit gain from gas kick in water based mud‎

  2. Pingback: Drill Pipe Pressure Schedule Calculation for Wait and Weight Well Control Method‎

  3. Pingback: Difference between True Vertical Depth (TVD) and Measured Depth (MD)‎

  4. shaida hussain says:

    thank u

Leave a Reply

Your email address will not be published. Required fields are marked *