Maximum pit gain from gas kick in water based mud

In water based mud, you can not only estimate the maximum surface casing pressure, but you are also be able to determine the maximum pit gain due to gas influx.

The following formula demonstrates how to figure out the maximum pit gain from gas influx in water based mud system.

maximum pit gain

 

Where

Maximum Pit Gain in bbl

P is formation pressure in psi.

V is original pit gain in bbl.

C is annular capacity in bbl/ft.

Kill Weight Mud in ppg

Let’s take a look at this following example in order to get more understanding regarding this topic.


Drill well with water based mud.

Pit gain = 20 bbl

Initial shut in casing pressure = 600 psi

Initial shut in drill pipe pressure = 500 psi

Current mud weight = 12.5 ppg

Hole depth = 6,000’MD/4,800’TVD

Hole diameter = 12-1/4 inch

Drill pipe = 5 inch

According to the data, you need to figure out the Kill Mud Weight , formation pressure, and annular capacity.

Kill Weight Mud = current mud weight + (shut in drill pipe pressure ÷ (0.052 x TVD))

Kill Weight Mud = 12.5 + (500 ÷ (0.052 x 4800)) = 14.5 ppg

Note: Please read the following link about kill weight mud -> well control formulas

Formation pressure = surface pressure + hydrostatic pressure

Formation pressure = 500 + (0.052 x 12.5 x 4800) = 3620 psi

Note: Please read the following link about formation pressure -> Formation Pressure from Kick Analysis

Determine annular capacity: Annular capacity = (12.252 – 52) ÷ 1029.4 = 0.1215 bbl/ft

Note: if you would like to understand annular capacity, please check out the following links -> Annular Capacity

Once you get all parameters required, you can add all of them into the equation like this.

Maximum Pit Gain = 98.5 bbl

Ref book: Drilling Formula Book Formulas and Calculations for Drilling, Production and Workover, Second Edition

Well Control Books

Related Post

Estimated mud weight required to safely drill the ... I have an interesting question to share with you about how to estimate minimum mud weight required to safely TD the well. The question is shown bel...
Bullheading Well Control Method Bullheading is one of the well control methods which may be utilized in some occasions in order to control the well. Concept of bullheading is to pump...
Lag Time for Drilling Business and How to Calculat... I got an email from Sanan asking me about how to calculate lag time. First of all, you need to know what the lag time is. Lag time is traveling t...
Cutting Slip Velocity Calculation Method 2 This is another method to determine cutting slip velocity. The process of calculation is quite different from the first method however it is still str...
Share the joy
  •  
  •  
  •  
  •  
  •  
  •  
  •  
  •  
  •  

About DrillingFormulas.Com

Working in the oil field and loving to share knowledge.
Tagged , . Bookmark the permalink.

2 Responses to Maximum pit gain from gas kick in water based mud

  1. Pingback: Drilling Formula Calculation Sheet V1.1‎

  2. Pingback: Drilling Formula Excel Sheet Version 1.2 Free Download‎

Leave a Reply

Your email address will not be published. Required fields are marked *