Casing Seat Selection – How To Select Casing Setting Depth

From the previous article, you’ve learnt about overall of casing design process and in this article we are going to discuss about how to select casing setting depth. The selection of casing string and setting depth is based on formation pore pressure and fracture gradient of the well.

casing seat selection fb

For the casing setting depth determination, pore pressure and fracture gradient are normally described in PPG (Figure 1).

Figure-1---Pore-Pressure-and-Fracture-Pressure-Plot

Figure 1 – Pore Pressure and Fracture Pressure Plot

 The solid lines in the chart are not accounted for safety factor; therefore, for the first step of casing seat design, safety margin must be applied. For this example, we will add 0.3 ppg for safety for both pore pressure and fracture gradient (Figure 2). You need to add the safety factor into formation pressure and subtract it from the fracture gradient. What’s more, the safety factor value may depends on where you work and how much confident in your data.

Figure-2---Pore-Pressure-and-Fracture-Pressure-Plot-with-Safety-Margin

Figure 2 – Pore Pressure and Fracture Pressure Plot with Safety Margin

The dashed lines are design range which will be used for the design. There are two ways to determine casing setting depths which are bottom-up and top-down method.

Bottom Up Casing Design

This design will start from the bottom of the well up to surface and the setting depths are designed within the safety factor limits (dotted lines). Starting at the bottom (formation pressure dashed line – Point A), draw a vertical line upward to fracture pressure dashed line – Point B (Figure 3). Casing should be set from 4,500’ TVD to 12,000’ TVD because you can reach TD (12,000’ TVD) with highest equivalent mud weight and you will not break the formation at shallow depth (4,500 TVD). We will apply this same concept to another string.

Figure-3---Bottom-Up-Design-Step-1

Figure 3 – Bottom Up Design Step#1

The next casing string is determined by drawing a horizontal line from Point B to intersect the pore pressure dashed line at Point C. Then draw a vertical line from Point C to the fracture gradient dashed line at Point D (Figure 4). The Casing must be set from 1,800’ TVD to 4,500’ TVD.

Figure-4---Bottom-Up-Design-Step-2
Figure 4
– Bottom Up Design Step#2

With the same idea, the next casing string is determined by drawing a horizontal line from Point D to Point E and a vertical line from Point E to Point F (Figure 5). The Casing must be set from surface to 1,800’ TVD.

Figure-5---Bottom-Up-Design-Step-3

Figure 5 – Bottom Up Design Step#3

Based on the bottom up design concept, we will need to have 3 strings of casing set at 1800’ TVD, 4500’ TVD and 12,000 TVD (Figure 6).

Figure-6---Bottom-Up-Design-Final

Figure 6 – Bottom Up Design Final

From the example, you can see how the bottom up casing design process is done. If you have the different pore pressure/fracture gradient, you can repeat the process for other casing strings until you reach surface casing.

Top Down Casing Design

This design will start from the surface of the well down to the bottom and the setting depths are designed within the safety factor limits (dotted lines). We start by drawing the vertical line from the facture gradient dashed line (point A) down to pore pressure dashed line (point B). See Figure 7. The first casing should be set from surface to 3,000’ TVD.

Figure-7---Bottom-Up-Design-Step-1

Figure 7 – Top Down Design Step#1

Next, draw the horizontal line from Point B to Point C located in the fracture dashed line curve. Then draw the vertical line from Point C to intersect the formation pressure dashed line curve at Point D. This is the section casing string which should be set from 3,000’ TVD to 6,000’ TVD (Figure 8).

Figure-8---Top-Down-Design-Step-2

Figure 8 – Top Down Design Step#2

Applying the same concept to the next string, draw the horizontal line from Point D to intersect the fracture gradient with safety factor chart at Point E and draw the vertical line from Point E to the target depth at Point F. The last casing string should be set from 6,000’ TVD to 12,000’ TVD (Figure 9).

Figure-9---Top-Down-Design-Step-3

Figure 9 – Top Down Design Step#3

 Based on the tow down design concept, we will need to have 3 strings of casing set at 3,000’ TVD, 6,000’ TVD and 12,000 TVD (Figure 10).

Figure-10---Top-Down-Design-Final

Figure 10 – Top Down Design Final

From the example, you can see how the top down casing design process is done. You can repeat the same process to determine the setting depth based on your fracture and pressure plot.

 Ref Book -> Applied Drilling Engineering Book special offer 

Tagged , . Bookmark the permalink.

About DrillingFormulas.Com

Working in the oil field and loving to share knowledge.

6 Responses to Casing Seat Selection – How To Select Casing Setting Depth

  1. Curd says:

    any pros/cons for bottom up & top down?

  2. Victor RUS says:

    Gents, I completely agree with top down and bottom up method except that you should use Bottom UP when you have reservoirs, if you don’t have reservoirs you should use top down method and then choose the CSG depth depending on lithology. This is simplest thing in CSG design, then we need to choose casing P110, L80, K55, etc. It would be great if you show us biaxial collapse, triaxial burst calculations etc and kick tolerance as well.

  3. Soran says:

    well done, this is really excellent and well explained casing setting depth selection procedure. However, would it be possible to demonstrate or provide us a real casing design calculation scenario for surface and intimidate section. please advise.

  4. AWAD says:

    well done.thanks a lot

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.