ACF – Annular Capacity Factor

AV – Annular Velocity

BF – Buoyancy Factor

BHA – Bottom Hole Assembly

BHP – Bottom Hole Pressure

BOP – Blow Out Preventor

BOPE – Blow Out Preventer Equipment

BPUTS – Bring Pumps Up To Speed

CC – Circulate and Condition mud

CLF – Choke Line Friction

CMW – Current Mud Weight

CP – Casing Pressure

DC – Drill Collar

Dh – Diameter of hole in inches

DP – Drill Pipe

DPP – Drill Pipe Pressure

ECD – Equivilant Circulating Density

EOB – End of Build

ESP – Estimated Stuck Point or Electical Submersible Pump

FCP – Final Circulating Pressure

FD – Fluid Density

FIT – formation integrity test

FOSV – Full Opening Safety Valve

FP – Formation Pressure

FrP – Friction Pressure

FV – Funnel Viscosity

GPM – Gallons Per Minute

HHP – Hydraulic Horse Power

HP – Hydrostatic Pressure

IBOP – Inside Blow Out Preventer

ICP – Initial Circulating Pressure

ISICP – Initial Shut-in Casing Pressure

KLF – Kill Line Friction

KMW – Kill Mud Weight

KOP – Kick Off Point

Lbs. – Pounds

LC – Lost Circulation

LCM – Lost Circulation Material

Len – Length in feet

LOT – Leak Off Test

MAASP – Maximum Allowable Annular Surface Pressure

MASP – Maximum Anticipated Surface Pressure

MD – Measured Depth

MGS – Mud Gas Separator

MI – Mud Increment

MISICP – Maximum Initial Shut-in Casing Pressure

MOP – Margin of Over Pull

MW – Mud Weight in ppg

NP – Neutral Point

OBM – Oil Based Mud

OMW – Original Mud Weight

OPT – Optimum

PG – Pressure Gradient

PI – Pressure Increment

POH – Pull Out Hole

PP – Pore Pressure

PPG – Pounds Per Gallon

RIH – Run In Hole

ROH – Run Out Of Hole

RPM – Rounds Per Minute

RSS- Rotary Steerible System

SCR – Slow Circulating Rate

SG – Specific Gravity

SICP – Shut-in Casing Pressure

SIDPP – Shut-in Drill Pipe Pressure

SOBM – Synthetic Oil Based Mud

SP – Surface Pressure

SPM – Strokes Per Minute

SPM Valve – Side Pocket Mandrel Valve

SPR – Slow Pump Rate

TDS – Top Drive System

TIH – Trip In Hole

TOC – Top Of Cement

TOF – Top Of Fish

TOH or TOOH – Trip Out Of Hole

TOL – Top Of Liner

TVD – True Vertical Depth

WL – Water Loss or Wire Line

WOB – Weight On Bit

WOC – Wait On Cement

WOO – Wait On Orders

WOW – Wait On Weather

YP – Yield Point

Tagged . Bookmark the permalink.

About DrillingFormulas.Com

Working in the oil field and loving to share knowledge.

2 Responses to Oil Field Abbreviation Mostly Used in the Rig

  1. ofigennoe.ru says:

    Best article, lots of intersting things to digest. Very informative

  2. marcello says:

    I am very interest with this website: Drilling formulas.com
    , and if there is another information about the Liner Hanger Calculation & formula how to Calculated it.
    I will be grateful, if I can get this Information.
    Before that, I want to say Thank You very much.
    God bless.

    Regards
    Marcello Stevano

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.