Trip Margin Calculation

Trip margin is an increment of drilling mud density to provide overbalance so as to compensate the swabbing effect while pulling out of hole.

You can quickly calculate how much trip margin required by this following simple equation.

Trip Margin = Mud Yield Point ÷ [11.7 x (Hole diameter – Drill pipe diameter)]

The unit of each parameter is as follows;

Trip Margin in ppg (pound per gallon)

Mud Yield Point in lb/100 sq ft

Hole diameter in inch

Drill pipe diameter in inch

Let’s try to determine the trip margin with the following information.

Mud Yield Point = 12 lb/100 sq ft

Hole diameter = 10 inch

Drill pipe diameter = 5 inch

Trip Margin = 12 ÷ [11.7 x (10 – 5)] = 0.2 ppg

Please find the Excel sheet  to calculate Trip Margin – -> Trip Margin Calculation Sheet

Ref book: Drilling Formula Book Formulas and Calculations for Drilling, Production and Workover, Second Edition

Related Post

Formulas for Wait and Weight Well Control Method There are some well control formulas that you need to know for wait and weight method.   1. Kill Weight Mud KWM = OMW + Where; KW...
Kill Weight Mud Kill Weight Mud or Kill Drilling Fluid Density is the mud weight required to balance formation pressure. The kill weight mud may be pumped into the we...
Basic Knowledge of Casing while Drilling (CwD) Casing while drilling (CwD) has been around for many years and it is one of proven technologies that can save both time and money. CwD is a process wh...
Adjusted maximum allowable shut-in casing pressure You calculate the maximum initial shut-in casing pressure (MISICP) based on the original mud weight before you start drilling ahead. Once you drill de...
Share the joy
  •  
  •  
  •  
  •  
  •  
  •  
  •  
  •  
  •  

About DrillingFormulas.Com

Working in the oil field and loving to share knowledge.
Tagged . Bookmark the permalink.

7 Responses to Trip Margin Calculation

  1. ramadan sayed says:

    it is good but we need law to provide how much i can increase mud weight without reach to M A A S P

  2. abualhuda says:

    i did not recieve any post last month any new news i am used t get the new post day after day

    abualham@aramco.com

  3. Hoss says:

    Hello,
    I have a question about trip margin. Is trip margin calculation necessary when TOOH ? A lot of companies standard procedure is to have 200-300 psi (0.5-0.8 ppg) of overbalance pressure (over the formation pressure) at all time. This means if 10 ppg mud is sufficient to control the formation pressure, 10+0.5= 10.5 or 10.8 ppg mud is used to drill over balance.
    My question is this:
    Is it still necessary to calculate the trip margin when TOOH if the hole is getting filled regularly ( every 75 psi of pressure drop) ?? So, even with mud weight that already considers overbalance pressure, do we still have to calculate “trip margin” and add it to the designed mud weight?

    • You need to know how much over balance of you mud weight is before POOH. If the overbalance is more than trip margin, it should be OK for pulling out. However, if you are so close to pore pressure, it is recommended to add more weight for a trip margin.

  4. rabea says:

    trip margin equal

    = overbalance/0.052/TVD + mud weight